Building Restoration
The building restoration work is proceeding well. The scaffolding and temporary roof have withstood the high winds and good progress has been made with stonework repairs and with the new roof and gutters. Repairs and improvements to underground drainage will start shortly. We are hopeful that all the work will be complete on programme by the 24th March.
WC
Planning permission has been granted for a stand-alone WC facility on the south side of the church opposite the door to the bell tower. This means that we can now invite tenders and make approaches to funding organisations for grant aid for this project.